Execution & sequencing
Pour cycles, shuttering rotation, crane time, monsoon planning. A tower is a rhythm — my job is keeping the beat when weather, vendors and drawings all miss theirs.
7-day slab cycle held, 8 floors
Civil engineer and project lead — twelve years from site trainee to delivering entire towers. 28 projects, ₹340 crore of built value, zero structural non-conformances — and a site log to prove every claim on this page.
Selected projects from the full register of 28. Completion certificates and client references available for every row.
| Project | Scale | Role | Delivery |
|---|---|---|---|
| IT park tower, Hinjewadi22 floors · commercial | 1.1M sq ft | Project lead | In progress · ahead |
| Residential township, Wagholi6 towers · 1,240 units | 2.4M sq ft | Deputy project manager | On time · 2024 |
| Elevated metro viaduct package4.2 km · 132 spans | ₹210 Cr | Section engineer | On time · 2021 |
| Industrial shed & warehouse, ChakanPEB · 40 t cranes | 380K sq ft | Site engineer | 3 wks early · 2018 |
| School campus, SataraCSR project · 3 blocks | ₹18 Cr | Site engineer | On time · 2016 |
"On time" means the certified completion date, not the press release. One project in 28 ran late — a 2019 mall, 11 weeks, monsoon flooding plus a contractor default. I list it because you'd find it anyway.
Pour cycles, shuttering rotation, crane time, monsoon planning. A tower is a rhythm — my job is keeping the beat when weather, vendors and drawings all miss theirs.
7-day slab cycle held, 8 floors
Cube registers, rebar inspections, pour cards, NCR closure. Concrete doesn't accept apologies — it accepts cover blocks, vibration and curing, checked every time.
0 structural NCRs in 12 years
Height work permits, toolbox talks in three languages, and the unpopular decisions — stopping a pour at 4 p.m. because the shoring didn't look right. It wasn't.
4.2M man-hours, 0 fatalities
RA bills, BOQ deviations, extra-item claims, subcontractor reconciliation. The technical half wins the site; this half keeps the project solvent.
₹34 Cr claims settled, documented
Baseline programmes, look-ahead schedules, catch-up plans that crews actually follow — because they were built with the foremen, not emailed to them.
26 of 28 projects on/ahead
Weekly reviews, design-query turnaround, the honest flag raised early. Clients renew with engineers whose bad news arrives before it becomes expensive.
3 clients, repeat projects
The stopped pour · 2022
Pumps primed, mixers queued, client on site — and a shoring tower on level 11 that had visibly settled 20 mm since morning. I cancelled the pour. It cost ₹4 lakh and a furious phone call. The structural consultant's inspection next day found two more towers on failing base plates. Nobody thanks you for the accident that didn't happen, so the log book has to.
The catch-up plan · 2023
Inherited a township package 11 weeks late after a contractor default. Rebuilt the programme around what the new crews could actually do: two extra shuttering sets, night pours for raft foundations, and a weekly commitment meeting where foremen set their own targets. We recovered the full 11 weeks in seven months — without a single safety incident during night work.
The claim file · 2024
Client disputed our extra-item claims on rock excavation. The difference between opinion and payment was three years of my site diaries: dated photos, joint measurement records, consultant instructions with signatures. Arbitration awarded 92% of the claim. Site engineering is half concrete, half evidence.
Photograph — helmet on, drawings in hand, on the slab
My father was a PWD draughtsman; our dinner table had blueprints under the plates. But the real conversion happened in my third year of engineering, on a site visit — watching a raft pour at midnight, 60 people moving like one organism. Software eats the world, but somebody still has to hold it up.
Twelve years later I've done the full arc: trainee measuring rebar spacing, section engineer on a metro viaduct, and now project lead on a 22-floor tower. The thing the arc taught me: sites don't fail on engineering. They fail on sequencing, cash flow and the conversations nobody wanted to have in week one.
"The structure will stand for sixty years. The shortcuts would have been invisible for five."
Experience
Tier-1 developer, Pune
22-floor commercial tower, 1.1M sq ft · 380-worker peak · currently 9 days ahead of baseline.
EPC contractor, Pune
Township (6 towers) + mall fit-out · recovered an 11-week delay · ₹6.8 Cr claim won in arbitration.
Infrastructure major, metro project
4.2 km elevated viaduct · 132 spans erected · zero LTI on my section.
Construction firm, Satara/Chakan
The foundation years: measurement books, cube tests, and learning Marathi site vocabulary.
Clients & consultants say
Structural consultant
"Rohit is the only site man who calls me before the problem, not after. The stopped pour in 2022 — his call, against every commercial pressure on that site — is why I take his projects."
Principal, structural consultancy, PuneWorked together on 4 projectsClient project head
"His weekly reports say what's actually happening — including what's late and whose fault it is, his own included. After two decades of contractor optimism, that's worth more than any Gantt chart."
VP Projects, developerRepeat client, 3 projectsOpen to project lead and PMC roles — high-rise, industrial or infrastructure. Pune preferred, site postings anywhere in India considered for the right project. Completion certificates and references ready.